top of page
Cost Breakdown
How We Arrived at Our Numbers
floor plan_edited.jpg
Phase II Church Projects
Costs
General Conditions
$190,300
General Requirements
$86,800
Demolition
$104,600
Altar Area Structural Mods
$47,500
New Mechanical Building Addition
$336,800
Interior Renovations / Restorations
$747,100
Church Ceiling
$200,000
Plumbing
$35,000
Fire Protection
$54,900
HVAC
$435,000
Electrical
$310,200
Scaffolding/Dance Floor
$50,000
Altar Installation, etc.
$54,000
Sound System
$132,000
Front Door Restoration
$20,000
Pews
$120,000
Low Voltage / Access Control
$50,000
Soft Costs
$200,000
Subtotal
$3,174,200
Contingency @ 10%
$317,420
Cost Escalation @ 3%
$95,226
Subtotal
$3,586,846
Builders Risk Insurance
$16,000
Contractor's Insurance & Risk Management
$71,400
Building Permit
$4,500
Construction Manager's Fee @ 6.5%
$233,145
Subtotal
$3,911,891
Potential Sales Tax Savings
($31,100)
Total
$3,880,791
Phase II Parking Lot Projects
Costs
General Conditions
$95,200
General Requirements
$43,400
Earthwork, Mobilization, etc.
$93,700
Site Utilities
$362,200
Paving & Curbs
$88,000
Landscaping & Irrigation
$97,500
Demolition
$25,000
Misc. Concrete & Sidewalks
$79,800
Electrical
$34,400
Demolition of Outbuilding
$17,595
Monument Signage
$45,000
Toilets and Portable
$100,000
Soft Costs
$200,000
Subtotal
$1,281,795
Contingency @ 10%
$128,180
Cost Escalation @ 3%
$38,454
Subtotal
$1,448,428
Builders Risk Insurance
$7,200
Contractor's Insurance & Risk Management
$32,000
Building Permit
$4,000
Construction Manager's Fee @ 6.5%
$94,148
Pre-Construction Services
$39,900
Subtotal
$1,625,676
Potential Sales Tax Savings
($11,300)
Total
$1,614,376
Phase II Total
$5,495,167
Phase III Parish Hall Projects
Costs
General Conditions
$190,300
General Requirements
$86,800
Concrete: FDN, Slab on Grade & Structural
$164,800
CMU Masonry
$404,600
Structural & Misc. Steel
$155,200
Misc. Metals / Dumpster Gates
$181,200
Carpentry & Mullwork
$46,100
Caulking, Sealants & Waterproofing
$18,500
Roofing
$21,000
Building Insulation
$19,700
Wood & Hollow Metal Doors
$98,600
Exterior StoreFront, Entrances & Glazing
$32,000
Drywall & Partitions
$250,000
Acoustical Treatments
$18,000
Tile Walls & Floors
$22,500
Flooring & Painting
$63,600
Canopies / Awnings / Sunscreens
$41,700
Building Specialties
$29,300
Equipment / Kitchen Eqpt.
$13,500
Furnishing
$7,600
Elevators
$95,000
Plumbing
$143,000
Fire Protection
$29,800
HVAC
$250,000
Electrical
$182,700
Low Voltage / Access Control
$25,000
Soft Costs
$200,000
Subtotal
$2,790,500
Contingency @ 10%
$279,050
Cost Escalation @ 3%
$83,715
Delay in Building Hall @ 9%
$251,145
Subtotal
$3,404,410
Builders Risk Insurance
$18,400
Contractor's Insurance & Risk Management
$82,100
Building Permit
$4,800
Construction Manager's Fee @ 6.5%
$221,287
Subtotal
$3,730,997
Potential Sales Tax Savings
($37,100)
Phase III Total
$3,693,897
bottom of page