top of page
Cost Breakdown
How We Arrived at Our Numbers
floor plan_edited.jpg
Work in Scope of AWC
Price
General Conditions
$580,865
General Requirements
$312,900
Unsuitable Soil - ALLOWANCE
$13,000
Earth/Site Work, Site Utils, Paving & Curbs, Fencing, Pavers
$858,700
Interior Scaffolding
$231,100
Demolition
$100,900
Landscape and Irrigation
$45,500
Concrete
$93,200
Altar Area Structural Mods
$55,400
Mechanical Room (Masonry + Steel)
$264,200
Interior Renovations
$765,535
Structural Repairs - ALLOWANCE
$70,000
Door Restoration
$30,900
Ceiling Repair (incl. Wood Trusses)
$406,000
Interior Plaster - ALLOWANCE
$95,000
Plumbing
$38,600
Fire Protection
$120,300
HVAC
$603,200
Electrical
$474,200
CCTV & Access Control, Sound, Low Voltage
$15,900
Subtotal
$5,175,400
Contingency
$258,000
Builders Risk Insurance
$27,900
Contractor's Insurance & Risk Management
$143,300
Building Permit
$62,200
Construction Manager's Fee @ 6.5%
$368,400
Guaranteed Maximum Price
$6,035,200
Typical Tax Savings
$60,352
Total of the AWC's Scope of Work
$5,974,848
Work to be Performed under Direction of the Church
Costs
Audio Visual & Security
$24,100
Altar Installation
$40,000
Pews
$129,000
Temporary Restrooms
$80,000
Other Soft Costs + Architectural Fees
$246,000
Monument Signage
$6,000
Total Project Cost
$6,499,948
Phase III Parish Hall Projects
Costs
General Conditions
$190,300
General Requirements
$86,800
Concrete: FDN, Slab on Grade & Structural
$164,800
CMU Masonry
$404,600
Structural & Misc. Steel
$155,200
Misc. Metals / Dumpster Gates
$181,200
Carpentry & Mullwork
$46,100
Caulking, Sealants & Waterproofing
$18,500
Roofing
$21,000
Building Insulation
$19,700
Wood & Hollow Metal Doors
$98,600
Exterior StoreFront, Entrances & Glazing
$32,000
Drywall & Partitions
$250,000
Acoustical Treatments
$18,000
Tile Walls & Floors
$22,500
Flooring & Painting
$63,600
Canopies / Awnings / Sunscreens
$41,700
Building Specialties
$29,300
Equipment / Kitchen Eqpt.
$13,500
Furnishing
$7,600
Elevators
$95,000
Plumbing
$143,000
Fire Protection
$29,800
HVAC
$250,000
Electrical
$182,700
Low Voltage / Access Control
$25,000
Soft Costs
$200,000
Subtotal
$2,790,500
Contingency @ 10%
$279,050
Cost Escalation @ 3%
$83,715
Delay in Building Hall @ 9%
$251,145
Subtotal
$3,404,410
Builders Risk Insurance
$18,400
Contractor's Insurance & Risk Management
$82,100
Building Permit
$4,800
Construction Manager's Fee @ 6.5%
$221,287
Subtotal
$3,730,997
Potential Sales Tax Savings
($37,100)
Phase III Total
$3,693,897
bottom of page